Board Meeting Minutes 7/29/2026
The final phase of our road paving project began today. D&H Asphalt will begin work on the entrance drive on Tuesday, September 29, with completion anticipated on Friday, October 2, weather permitting. The current schedule is: * Tuesday & Wednesday: Mill existing pavement and grade the road subgrade * Thursday:
Due to rainy weather, completion of Phase 2 of the road project has been delayed. Residents may continue to drive on the affected section of road through the weekend. However, all vehicles must be removed from the road by 7:00 AM on Monday morning so construction crews can place
Dear Quail Run Residents, This is a reminder that road construction is scheduled to begin tomorrow, Tuesday, September 15, at 7:00 AM. You may view the complete schedule by clicking here. The Board confirmed with Engineering Technologies today that pulverizing will begin as scheduled. All vehicles must be moved